Projects›Solar Farm – Rajasthan

Solar Farm – Rajasthan

Grid-connected solar project | AMS-I.D | 2023 – 2024

Preflight Report

Solar Farm – Rajasthan | 2023 – 2024

CarbonFlow Preflight

Verification Readiness Preflight Report

Solar Farm – Rajasthan • Monitoring Period: 01 Jan 2023 – 31 Dec 2024

Readiness Score
78%
● 3 Critical▲ 5 Material✓ 2 Minor
Documents Processed:12
Extracted Data Points:48
Report Generated:12 Jun 2024, 14:45

Executive Summary

This Verification Readiness Preflight Report summarizes the automated compliance and data integrity assessment conducted for Solar Farm – Rajasthan under UNFCCC methodology AMS-I.D.

Action Required Prior to Verification

3 critical findings remain unresolved, notably a 3,225 MWh net electricity export discrepancy between the annual monitoring report summary and monthly substation meter logs. Reconciling this figure is mandatory before independent auditor submission.