Projects›Solar Farm – Rajasthan

Solar Farm – Rajasthan

Grid-connected solar project | AMS-I.D | 2023 – 2024

Critical
CALC-001Open

Net electricity export mismatch

The net electricity exported in the monitoring report (152,345 MWh) does not match the sum of monthly meter readings (149,120 MWh).

3 sources
Suggested RemediationReconcile the report total with the monthly meter log and correct whichever figure is wrong.
Evidence Citations View in Evidence Viewer
“Extracted data for rule CALC-001 contradicts source document.”
Review action: